Jorge A. Parra / engineering tools

Home / Risk / Risk Priority Number

Risk Priority Number (RPN) in FMEA: formula, calculator, and what it hides

The Risk Priority Number ranks the failure modes of an FMEA, DFMEA or PFMEA by multiplying three ratings: severity, occurrence and detection. Here is how it is calculated, what range it covers, how teams use it, and the three things the textbooks leave out.

What is RPN in FMEA?

In a Failure Mode and Effects Analysis, each failure mode is rated on three 1 to 10 scales:

  • Severity (S): how serious the effect is, 10 the worst.
  • Occurrence (O): how often the cause or the failure happens, 10 the most frequent.
  • Detection (D): how hard it is to detect before it reaches the customer, 10 the hardest.
RPN = Severity × Occurrence × Detection

The result runs from 1 to 1,000. The failure modes are sorted from the highest RPN down, and the team acts on the top of the list, often on every RPN of 100 or 120 and above. Example: S 5, O 3, D 6 gives RPN 90.

RPN calculator

Choose the three ratings. The calculator gives the RPN, then shows what the number does not tell you.

Ratings 1 to 10, as in most FMEA manuals.

RPN

90

SAME RPN, DIFFERENT RISKS

RPN+, THE SAME RATINGS PLACED

What the textbooks do not tell you

1. A thousand combinations, 120 numbers

Three ratings from 1 to 10 make 1,000 combinations, but their products take only 120 different values. RPN 60, 72 and 120 are each shared by 24 different combinations. A sorted list of RPNs is a list of ties.

2. A rattle and a catastrophe score the same

A panel that rattles constantly (S 1, O 10, D 1) and a failure that kills once a decade (S 10, O 1, D 1) both score RPN 10. Multiplication forgets which factor was large, and severity is the one that should never be forgotten.

3. The threshold lets the worst through

With an action threshold of 100, 23 combinations with severity 10 still score below it, and 107 combinations with severity 4 or less score above it. The rule meant to focus the team on what matters sends it to the minor failures first.

The defects are old news among statisticians: Donald Wheeler showed in 2011 that multiplying ordinal ratings is not a valid operation. In 2019 the AIAG & VDA FMEA Handbook retired the RPN, and replaced it with Action Priority: three buckets, high, medium and low, which remove the multiplication and keep the ties. See Action Priority compared.

4. A crooked tool is worse than no tool

Without a tool, a team knows it is guessing, so it stays careful and keeps arguing. A crooked tool gives the guess a number. The number looks like evidence, gets signed, and ends the argument. The rare catastrophe ranked below a nuisance is not just missed: it is screened out with a record that proves due diligence.

A score that keeps every combination: RPN+

RPN+ = 100 × Severity + 10 × Occurrence + Detection

The same three ratings, placed side by side instead of multiplied. RPN+ 754 is severity 7, occurrence 5, detection 4: the score reads back to its ratings. Every one of the 1,000 combinations gets its own number, from 111 to 1110, and no failure of lower severity can ever outrank one of higher severity. Severity decides, occurrence orders, detection breaks ties.

RPN+ is part of Structured Risk Analysis (SRA), a fourteen-step method that starts from the requirement, splits counted evidence from expert estimates, and screens on impact alone. Its scores are free to use, with attribution. The classical RPN is still printed beside every RPN+, for whoever asks.

Questions people ask about RPN

What is the RPN formula in FMEA?
RPN = Severity × Occurrence × Detection. Each factor is rated from 1 to 10, so the RPN runs from 1 to 1,000. Higher numbers are treated as higher priority.
What is a good or acceptable RPN?
There is no universal value. Many companies act on RPNs of 100 or 120 and above, but the threshold is a local choice. A threshold on RPN can let a catastrophic failure pass: with severity 10, 23 combinations still score below 100.
Is RPN still used after the AIAG & VDA FMEA Handbook?
The 2019 AIAG & VDA FMEA Handbook replaced RPN with Action Priority (high, medium, low), and some customers still ask for RPN alongside it. Action Priority removes the multiplication but keeps ties: it sorts every failure mode into three buckets.
What is the maximum RPN?
1,000, for severity 10, occurrence 10 and detection 10. But of the 1,000 possible combinations, only 120 different RPN values exist.
Why do two different risks get the same RPN?
Because multiplication hides which factor is large. A constant rattle (S1, O10, D1) and a once-a-decade catastrophe (S10, O1, D1) both score RPN 10. RPN 120 alone is shared by 24 different combinations.
Is there an alternative to RPN that keeps severity first?
RPN+ places the three ratings instead of multiplying them: RPN+ = 100 × Severity + 10 × Occurrence + Detection. Every combination gets its own score, and no failure of lower severity can outrank one of higher severity. It is free to use, with attribution.

The 5x5 risk matrix · Action Priority · Back to Risk

Sources

  • D. J. Wheeler, “Problems With Risk Priority Numbers,” Quality Digest, 2011.
  • AIAG & VDA, FMEA Handbook, first edition, 2019: Action Priority in place of the RPN.
  • MIL-STD-882C, System Safety Program Requirements, 1993, Appendix A: one index for every cell, and the warning against products.
  • The counts on this page (120 values, 24-way ties, the threshold cases) are enumerations of all 1,000 combinations.